Long-term cooperation both as a general contractor and a contractor for electrical and low-voltage installations on projects such as:
INTEL lease area – execution of electrical installations along with electrical site management; execution period: 01–04.2011
ALLCON@PARK3 (Gdańsk, Słowackiego St.) – execution of electrical installations and laboratory power supply on the 3rd and 4th floors of Building A; execution period: 12.2011–03.2012
ALLCON@PARK complex – execution of electrical works for the reconstruction of rooms in buildings IGK1 and IGK2; execution period: 06–12.2012
ALLCON@PARK3, Wing B (1st and 4th floors) – execution and assembly of electrical and power installations, including transformer station reconstruction; execution period: 11.2012–01.2013
ALLCON@PARK3 – execution and assembly of electrical installations for the fit-out of the 2nd floor (Wing A) and 2nd and 3rd floors (Wing B); execution period: 09.2014–06.2015
MEGALAB 2 technical laboratory (Building IGK 1, Gdańsk) – general contracting for the construction of the laboratory; execution period: 05.10.2019
Building IGK7 – general contracting for the construction of two computer laboratories, a warehouse and staff building, and 9 construction structures with technical equipment and necessary infrastructure; execution period: 06.2022–03.2023
INTEL Campus in Gdańsk – general contracting for the relocation of two sports fields, including landscaping and the supply and installation of outdoor furniture; execution period: 04.09.2023
Building IGK2 – replacement of AHU units (Air Handling Units); execution period: 07.2024–02.2025